Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for February February 2017 BLUE
Monthly Report January 2017 GREEN GREEN GREEN GREEN
Monthly Report December 2016 GREEN GREEN GREEN GREEN
Report for Oct 2016 October 2016 GREEN GREEN GREEN GREEN
Report for Sept 2016 September 2016 AMBER AMBER GREEN AMBER
Report for August August 2016 AMBER GREEN GREEN AMBER
Report for July 2016 July 2016 GREEN GREEN GREEN GREEN
Report for June 2016 June 2016 GREEN GREEN GREEN GREEN
Report for May 2016 May 2016 AMBER GREEN GREEN AMBER
Report for April 2016 April 2016 GREEN GREEN GREEN GREEN
Report for Mar 2016 March 2016 GREEN GREEN GREEN GREEN
Report for Feb 2016 February 2016 GREEN GREEN GREEN GREEN
Report for January 2016 January 2016 GREEN
Report for December 2015 December 2015 GREEN
Report for November 2015 November 2015 GREEN GREEN GREEN RED
Report for October 2015 October 2015 AMBER GREEN GREEN AMBER
Report for September 2015 September 2015 GREEN GREEN GREEN GREEN
Report for August 2015 August 2015 AMBER GREEN GREEN AMBER
Report for July 2015 July 2015 AMBER GREEN GREEN AMBER
Report for March 2015 March 2015 GREEN GREEN GREEN GREEN
Report for February 2015 February 2015 GREEN GREEN GREEN GREEN
Report for January 2015 January 2015 GREEN GREEN GREEN GREEN
Report for December 2014 December 2014
Report for November 2014 November 2014 GREEN GREEN GREEN GREEN

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance