eCommerce Implementation (PPS008)
eCommerce Implementation (PPS008)
Home
Projects
eCommerce Implementation (PPS008)
Status
Report for February
Report for February
Report Date
February 2017
Project now closed
Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Mar 9, 2017
Project Info
Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Initiate
No documents
Plan
Project Brief
Execute
Build Test Document (SqImport)
Deployment Checklist
Integration Test Document
UAT Document
User Acceptance Test Plan
Business Requirements
System Design Specification
Build Test Document
Implementation Plan
Implementation Plan (SqImport)
Deliver
No documents
Close
Completion Report
Other
No documents