Report for July 2015
- Report Date
- July 2015
Achievements in Last Period
- Both Systems and Business Analysis has taken place.
Issues
- Due to illness in Project Services (project manager), the progress of the project has stalled over the last month however this is now being picked up again.
Next Steps
- As some of the milestones have been missed due to absence, the project will require a replan and another estimate. The milestones originally given were indicative and will be reviewed in light of recent analysis.
- The project sponsor is currently on annual leave so new milestones will be reported in August.
Milestones
TBA
Amber Status: The project milestones below need to be replanned following the project managers illness, the Project Sponsor is however on annual leave so revised milestones cannot be agreed until his return.
- Approved budget
- 154.0 days
- Activity this month
- 0.0 days
- Activity this year
- 36.3 days
- Activity to date
- 36.3 days
- Estimate to complete current year
- 117.7 days
- Estimate to complete future years
- 0.0 days