Report for Oct 2016
- Report Date
- October 2016
Achievements in Last Period
- New workflows switched on.
- Milestones / budget adjusted to reflect new roll-out timescales.
Issues
- Issue with code combination upload to Sciquest. Fix in progress.
- Issue with PO Printing in eFin. FIXED.
- Issue with fields > 20 characters. FIXED.
Next Steps
- Deployment Sign-off
- Suspend Project, until roll-out complete and de-commission activity can commence.
- Migrate existing Sciquest users to new workflows.
- Migrate PECOS users to Sciquest.
- Decommission PECOS.
The project is now reporting GREEN.
- Approved budget
- 360.0 days
- Activity this month
- 16.4 days
- Activity this year
- 55.6 days
- Activity to date
- 320.9 days
- Estimate to complete current year
- 35.5 days
- Estimate to complete future years
- 0.0 days