Report for November 2015
- Report Date
- November 2015
Achievements in Last Period
- Revised project plan and resource plan created
- Build for POs and GRs deliverables started
- Revised project budget approved
- Draft TAD created and with Technology Management for approval
Issues
- Revised project plan has extended milestones past desired dates and may result in decommisioning of PECOS in 16/17. This is to be reviewed with development to determine if a second developer could be assigned to reduce timescales.
- Full design sign off not completed as TAD not avaiable. Systems Design Document signed off and once approval from Technology Management has been received then full sign off will be requested by email.
Next Steps
- Review resourcing options with development to determine if timescales can be reduced by assigning a seperate developer for the Users, Codes and combinations
- Revise project plan and circulate to Estates and Sciquest for feedback
- Final Design sign off
- continue build
Milestones
17-Feb-2016 | Build for Purchase Orders and Good's Receipt complete |
24-Mar-2016 | Acceptance Sign Off for Purchase Orders and Goods Receipts |
04-Apr-2016 | Deploy Purchase Orders and Goods Receipts to LIVE |
04-Apr-2016 | Build Complete for Users, Codes and Combinations |
25-Apr-2016 | Post Deployment Sign off Review - POs & GRs |
06-May-2016 | Acceptance Sign Off for Users, Codes and Combinations |
16-May-2016 | Deploy Codes, Users and Combinations to LIVE |
02-Jun-2016 | Post Deployment Sign-off Review - Codes, Users and Combinations |
24-Jun-2016 | Training of PECOS users complete |
08-Jul-2016 | Decommissioning of PECOS |
29-Jul-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days