Report for November 2015

Report Date
November 2015

Achievements in Last Period

  • Revised project plan and resource plan created
  • Build for POs and GRs deliverables started
  • Revised project budget approved
  • Draft TAD created and with Technology Management for approval

 

Issues

  • Revised project plan has extended milestones past desired dates and may result in decommisioning of PECOS in 16/17. This is to be reviewed with development to determine if a second developer could be assigned to reduce timescales. 
  • Full design sign off not completed as TAD not avaiable. Systems Design Document signed off and once approval from Technology Management has been received then full sign off will be requested by email. 

 

Next Steps

  • Review resourcing options with development to determine if timescales can be reduced by assigning a seperate developer for the Users, Codes and combinations
  • Revise project plan and circulate to Estates and Sciquest for feedback
  • Final Design sign off 
  • continue build

 

Milestones

17-Feb-2016Build for Purchase Orders and Good's Receipt complete
24-Mar-2016Acceptance Sign Off for Purchase Orders and Goods Receipts
04-Apr-2016Deploy Purchase Orders and Goods Receipts to LIVE
04-Apr-2016Build Complete for Users, Codes and Combinations
25-Apr-2016Post Deployment Sign off Review - POs & GRs
06-May-2016Acceptance Sign Off for Users, Codes and Combinations
16-May-2016Deploy Codes, Users and Combinations to LIVE
02-Jun-2016Post Deployment Sign-off Review - Codes, Users and Combinations
24-Jun-2016Training of PECOS users complete
08-Jul-2016Decommissioning of PECOS
29-Jul-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance