Report for January 2016

Report Date
January 2016

Achievements in Last Period(no report in Dec so since end Nov)

  • Second developer assigned to reduce the risk of the key project milestones slipping
  • Build for POs integration progressing
  • Build for Users, Codes and Combinations integration in progress
  • Discussions with Finance and Procurement relating to Codes and Combinations 
  • New User creation process mapped with Procurement
  • Draft TAD reviewed by Technology Management

 

Issues

  • Project milestones replanned to reflect minor delays to progress on the PO build (resolved)
  • Technology Management feedback was provided for the TAD. There is concern over the size and format of the overall Finance TAD, although not specific to this project this will need to be discussed further before design sign off can be formally agreed for the TAD. (ongoing)
  • It has been agreed that Estates users will be trained as a priority before retraining PECOS users to be transferred to SciQuest. The decommisioning of PECOS is now planned for Oct 2016. Remaining tasks will be replanned (ongoing)

 

Next Steps

  • Review full project plan and update
  • Complete full risk review
  • start Goods Receipt build
  • complete Codes, Combinations and Users integration
  • draft technical build and implementation documentation
  • Peer testing of the PO, GR and Codes, Combinations and Users integrations. 

 

Milestones

07-Mar-2016Build for Purchase Orders and Good's Receipt complete
04-Apr-2016Build Complete for Users, Codes and Combinations
15-Apr-2016Acceptance Sign Off for Purchase Orders and Goods Receipts
26-Apr-2016Deploy Purchase Orders and Goods Receipts to LIVE
13-May-2016Acceptance Sign Off for Users, Codes and Combinations
16-May-2016Post Deployment Sign off Review - POs & GRs
23-May-2016Deploy Codes, Users and Combinations to LIVE
02-Jun-2016Post Deployment Sign-off Review - Codes, Users and Combinations
24-Jun-2016Training of PECOS users complete
24-Oct-2016Decommissioning of PECOS
11-Nov-2016Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
257.0 days
Activity this month
21.0 days
Activity this year
93.0 days
Activity to date
129.0 days
Estimate to complete current year
122.0 days
Estimate to complete future years
10.0 days

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance