Report for August 2015

Report Date
August 2015

Achievements in Last Period

  • The Gap Analysis has been completed and is with the Project Spnsor for approval
  • The Business Requirements Document has been completed and signed-off
  • Systems Analysis and Design are currently underway
  • The project has been replanned and the new milestones are listed below

Issues

  • Although the new milestones and plan have been created, these need to be signed off by IS Apps so the project is marked as AMBER

Next Steps

  • Completion of the Systems Analysis and Design
  • More detailed plans to be created on the business-specific tasks related to the project

Milestones

Target dateTitle
09-Sep-2015Gap Analysis Review Complete
11-Sep-2015Business Requirements Sign-off
11-Sep-2015Project replan
18-Sep-2015Communications Plan
05-Oct-2015Systems Analysis and Design Review
06-Nov-2015Project Build Review Sign-off
04-Dec-2015Integration/ Configuration Sign-off
15-Jan-2016Acceptance Sign-off Review
29-Jan-2016Deployment
12-Feb-2016Deployment Sign-off Review
26-Feb-2016Training of PECOS users complete
31-Mar-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
154.0 days
Activity this month
12.0 days
Activity this year
12.0 days
Activity to date
48.3 days
Estimate to complete current year
105.7 days
Estimate to complete future years
0.0 days

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance