Report for August 2015
- Report Date
- August 2015
Achievements in Last Period
- The Gap Analysis has been completed and is with the Project Spnsor for approval
- The Business Requirements Document has been completed and signed-off
- Systems Analysis and Design are currently underway
- The project has been replanned and the new milestones are listed below
Issues
- Although the new milestones and plan have been created, these need to be signed off by IS Apps so the project is marked as AMBER
Next Steps
- Completion of the Systems Analysis and Design
- More detailed plans to be created on the business-specific tasks related to the project
Milestones
Target date | Title |
---|---|
09-Sep-2015 | Gap Analysis Review Complete |
11-Sep-2015 | Business Requirements Sign-off |
11-Sep-2015 | Project replan |
18-Sep-2015 | Communications Plan |
05-Oct-2015 | Systems Analysis and Design Review |
06-Nov-2015 | Project Build Review Sign-off |
04-Dec-2015 | Integration/ Configuration Sign-off |
15-Jan-2016 | Acceptance Sign-off Review |
29-Jan-2016 | Deployment |
12-Feb-2016 | Deployment Sign-off Review |
26-Feb-2016 | Training of PECOS users complete |
31-Mar-2016 | Closure |
- Approved budget
- 154.0 days
- Activity this month
- 12.0 days
- Activity this year
- 12.0 days
- Activity to date
- 48.3 days
- Estimate to complete current year
- 105.7 days
- Estimate to complete future years
- 0.0 days