Report for September 2015
- Report Date
- September 2015
Achievements in Last Period
- Systems Analysis and Design are currently underway and options are being explored to deliver the business requirements
- Communications with the users is underway by the Procurement Team
- Discussions between the Project Sponsor, Project Manager and the supplier have taken place
- Project Manager has met with the Procurement Team to help identify the tasks for Procurement within the larger project plan
Issues
- There is a potential change to scope for this project as there are several options for the delivery which are currently being analysed. These will be formally managed as a change to scope if required.
Next Steps
- Project Sponsor to issue Gap Analysis
- Completion of the Systems Analysis and Design
- Raise any relevant changes to the project scope
- Share the Project plan with SciQuest
Milestones
Target date | Title |
---|---|
09-Oct-2015 | Systems Analysis and Design Review |
09-Oct-2015 | Project replan |
06-Nov-2015 | Project Build Review Sign-off |
04-Dec-2015 | Integration/ Configuration Sign-off |
15-Jan-2016 | Acceptance Sign-off Review |
29-Jan-2016 | Deployment |
12-Feb-2016 | Deployment Sign-off Review |
26-Feb-2016 | Training of PECOS users complete |
20-May-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days