Report for December 2014

Report Date
December 2014

Achievements in Last Period

  • Meeting with Project Sponsor to discuss requirements.
  • Work has started on the project brief and project plan.

Issues

  • There has been a delay to the project brief due to resource issues.

Next Steps

  • Complete and agree the project brief, project estimate, project plan and milestones with project sponsor.
  • Carry out Business Analysis and requirements gathering.
Project Status
Activity
Approved budget
182.0 days
Activity this month
3.0 days
Activity this year
4.4 days
Activity to date
4.4 days
Estimate to complete current year
177.6 days
Estimate to complete future years
0.0 days

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance