Report for March 2015
- Report Date
- March 2015
Achievements in Last Period
- Communications with both the SciQuest Supplier and ABS (eFinancials Supplier) has taken place.
- This has fed into the gap analysis regarding both systems.
- The project brief has been completed and signed-off.
- The Project Team has worked on creating a detailed Project Plan.
- Project Services have provided a presentation of JIRA and its use for managing project tasks for the whole project team.
- Work within eProcurement has continued in terms of supplier migration.
- Work has continued on the Gap analysis
Issues
- Due to illness during the week commencing the 6th of April in Project Services, the gap analysis has been delayed.
Next Steps
- Finish the detailed project plan.
Milestones
Target date | Title |
---|---|
24-Apr-2015 | Gap Analysis Review Complete |
04-May-2015 | Systems Analysis and Design Sign-off *Indicative* |
15-Jun-2015 | Project Build Review Sign-off *Indicative* |
20-Jul-2015 | Integration/ Configuration Sign-off *Indicative* |
26-Aug-2015 | Acceptance Sign-off Review *Indicative* |
06-Oct-2015 | Deployment *Indicative* |
26-Oct-2015 | Deployment Sign-off *Indicative* |
06-Nov-2015 | Closure *Indicative* |
- Approved budget
- 154.0 days
- Activity this month
- 10.4 days
- Activity this year
- 25.1 days
- Activity to date
- 25.1 days
- Estimate to complete current year
- 68.9 days
- Estimate to complete future years
- 60.0 days