Monthly Report

Report Date
January 2017

Achievements in Last Period

  • Codes / combination fixes applied in LIVE.

Issues

  • None

Next Steps

  • Deployment Sign-off
  • Close Project

The project is now reporting GREEN.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
355.0 days
Activity this month
2.5 days
Activity this year
68.9 days
Activity to date
334.4 days
Estimate to complete current year
3.6 days
Estimate to complete future years
0.0 days

Project Info

Project
eCommerce Implementation (PPS008)
Code
PPS008
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
11-Nov-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Feb-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance