Report for February 2015
- Report Date
- February 2015
Achievements in Last Period
- Discussion around scope and requirements for the work have taken place, with an additional option for delivery being considered by the project.
- The project brief has been revised to reflect the changes and is currently being issued.
Issues
- Due to the inclusion of another option for the delivery of the work, there has been a delay to the requirements analysis.
Next Steps
- Obtain sign-off for the project brief.
- Continue with the Business Analysis and requirements gathering phase.
- Business to determine the best solution for the project implementation.
Milestones
Target date | Title |
---|---|
20-Mar-2015 | End of Planning |
- Approved budget
- 180.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days