Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for January 2020 January 2020 AMBER AMBER AMBER AMBER No Change
Report for December 2019 December 2019 AMBER AMBER GREEN AMBER Significant
RSS042 - Data Safe Haven ISO27001 November 2019 AMBER AMBER GREEN AMBER Significant
RSS042 - Data Safe Haven ISO27001 October 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 September 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 August 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 July 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 June 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 May 2019 GREEN GREEN GREEN GREEN Within Tolerance
RSS042 - Data Safe Haven ISO27001 April 2019 AMBER GREEN GREEN AMBER Within Tolerance
Planning and Delivery are in Progress. March 2019 AMBER GREEN GREEN AMBER Within Tolerance
Planning and Delivery are in Progress. February 2019 GREEN AMBER AMBER AMBER Within Tolerance
Planning and Delivery are in Progress. January 2019 GREEN AMBER AMBER AMBER Within Tolerance
ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way. December 2018 GREEN AMBER AMBER AMBER Within Tolerance
ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way. November 2018 GREEN AMBER AMBER AMBER Within Tolerance
ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way. October 2018 GREEN AMBER AMBER AMBER Within Tolerance
ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way. January 2018 GREEN AMBER AMBER AMBER Within Tolerance