Planning and Delivery are in Progress.

Report Date
January 2019

Report For December 2018

 

Achievements in the last Period.

Technical Controls

SIEM – Splunk Neil Kell has highlighted a standard, GPG13 (Good practice guide) that would satisfy our ISO27001 SIEM guidelines. Splunk has a plugin app for this standard. We discussed this with the Splunk service team who will look for the ‘right’ consultant to assist us with this. Splunk stated that they will give us an instructional pdf to enable us to integrate splunk with our Log Insight logs on the 4th of Feb. Once Stephen has this he’ll try it out. Splunk were pretty non-committal as to when they would be able to give us the required consultant to support us.

Management Cluster Upgrade We have a quote for an R630. We need this requoted with more RAM. We need a quote for the VMWare required to run on this Hypervisor.

Cage. This is ordered and we should get a delivered date over the next week or two. Paul Hutton is aware.

IDS / IPS This isn’t going ahead. Stephen has document the reasons.

 Encryption. We have a meeting with Thales (through Softcat) on Wednesday. I would hope after that we will have an idea of direction. The disks to support the TSM Encryption have been ordered and Ian Wilkes is here from the 5th Feb. I would hope to be able to publish a plan to complete for this by the end of Feb.

 

Governance Project Board and Security Working Group are defined and in place.

Policy and Procedures These are in progress. This is a large task that will need more resource than has been applied to it to date. Hard to do any level of detailed planning on this due to lack of resources. Very soft completion date of end of May.

Incident Management Meetings on-going trying to clarify the status of required standards and procedures from a Data Safe Haven Perspective.

 

Key Tasks For Next Period

  • As above.

Issues

Lack of resource in both the Technical and Ops areas is holding up progress.

 

Milestones

Stage Milestone Due Date Previous Date Complete  
Plan Complete Plan. 28-Feb-2019 No date available No

view

Deliver Governance 28-Feb-2019 No date available No

view

Deliver Roles and Responsibilities 31-Mar-2019 No date available No

view

Deliver Performance Metrics 30-Apr-2019 No date available No

view

Deliver Incident Management. 31-May-2019 No date available No

view

Deliver Complete Policy and Procedures. 31-May-2019 No date available No

view

Deliver Implement SIEM (Splunk) 30-Jun-2019 No date available No

view

Deliver Cryptography and Key management 31-Aug-2019 No date available No

view

Deliver Asset Management 30-Nov-2019 No date available No

view

Close Close Project 31-Dec-2019 No date available No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Lack of resource in the Technical area is holding up our ability to clarify technical requirements and move forward.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation