ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way.

Report Date
November 2018

Report For November 2018

 

Achievements in the last Period.

  • The 2nd Iteration of The Security Risk Assessment has been delivered.
  • We reviewed the above and the accompanying report and agreed an initial set of actions to push us toward an agreed plan.
  • We have ben instructed that Splunk will be the technical solution we use for SIEM.
  • Initial plan is in progress. With meeting planned to initiate the primary work packages:
  •     Governance
  •     Review what governance is required around the ISMS.
  •     I believe the right questions have been asked and once we havethe answers we should be able to sign this off and get the governance in place.
  •     Roles And Responsibilities.
  •     Tied in with the above.
  •     Statement Of Applicability.
  •     Not yet started.

 

Key Tasks For Next Period

  • Get high level requirements for SIEM from the technical team and progress with Splunk.
  • Progress the Governance, Roles and Responsibilities, Statement of Applicability and HR Work packages.
  • Refine and agree plan to certification.
  • Initiate Policies and Procedures now we have visibility of the standards.

Issues

  • The Technical have been pretty well pulled into other non DSH work that is currently deemed higher priority. This will have significant impact potentially until the end of the year.

 

Milestones

Stage Milestone Due Date Previous Date Complete  
Deliver Complete Primary Work Packages. 31-Jan-2019 No date available No

view

Initiate Initiate Traunch 2 Work Packages. 31-Jan-2019 No date available No

view

Analyse Clarify Dependency for Policy and Procedures. 31-Jan-2019 No date available No

view

Analyse Clarify Dependency for Incident Management. 31-Jan-2019 No date available No

view

Deliver Complete Traunch 2 Work Packages. 31-Jul-2019 No date available No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Lack of resource in the Technical area is holding up our ability to clarify technical requirements and move forward.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation