RSS042 - Data Safe Haven ISO27001

Report Date
October 2019

 

Audit and Review Planning.

Part 1 of the ISO27001 audit was completed last week with three minor inconformity's. All three will be closed in time fro part 2 which is next week and thus far we believe we are on target to pass.

We will find out on the last day. (Thursday 7th).

Document Management

As per plan, we have all our documents in the Subversion repository. Reviewed and signed off.

SIEM (Splunk)

We have progressed our Splunk development to a point where we believe we have more than satisfied the ISO27001 requirement. We will probably continue to expand on its use next year. But for the time being its complete.

 

DSH Change (CAB) process.

This has been drafted and reviewed and implemented.

Secure Configuration (Patching).

We have all the required processes in place and are patching. The backlog is huge though are we don't believe we'll get on top of this with current resource levels.

DSH Physical Security Procedures

This is complete and ready for the audit.

Cryptography

Encryption appliances have been racked, stacked and power up. We will now re engage with the vendor and agree a plan to implement encryption. This will not be done by the October audit which, we are told, shouldn’t be an issue as its planned. Stephen Giles has documented how Data Safe Haven meets University Encryption standards. We have an ongoing requirement to upgrade the encryption level from TLS1.1 to TLS1.2. Stephen Giles is investigating this at the moment. This is an NHS Lothian Requirement as well as being required to meet the UoE Defined Standard.

 

Issues & Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner  
1 Patching requriement to the Defined Standard is not achievable with current resource levels. GREEN GREEN Open Reduce David Fergusson

view

Key Tasks For Next Period

Part 2 of the audit and get certified.

 

Milestones

Stage Milestone Due Date Complete  
Deliver Internal Audit - Part 2 05-Nov-2019 No

view

Deliver Cryptography and Key management 27-Dec-2019 No

view

Close Close Project 31-Dec-2019 No

view

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation