ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way.

Report Date
January 2018

Report For January 2018

 

Achievements in the last Period.

Technical Controls

SIEM – Splunk Neil Kell has highlighted a standard, GPG13 (Good practice guide) that would satisfy our ISO27001 SIEM guidelines. Splunk has a plugin app for this standard. We discussed this with the Splunk service team who will look for the ‘right’ consultant to assist us with this. Splunk stated that they will give us an instructional pds to enable us to integrate splunk with our Log Insight logs on the 4th of Feb. Once Stephen has this he’ll try it out. Splunk were pretty non-committal as to when they would be able to give us the required consultant to support us.

 Management Cluster Upgrade We have a quote for an R630. We need this requoted with more RAM. We need a quote for the VMWare required to run on this Hypervisor.

 Cage. This is ordered and we should get a delivered date over the next week or two. Paul Hutton is aware.

IDS / IPS This isn’t going ahead. Stephen has document the reasons.

 Encryption. We have a meeting with Thales (through Softcat) on Wednesday. I would hope after that we will have an idea of direction. The disks to support the TSM Encryption have been ordered and Ian Wilkes is here from the 5th Feb.

Governance First Security Working Group is scheduled for next week. Agenda will be agreed and circulated beforehand. Project Board will be reinitialised two weeks later. ToRs have been created and distributed for both meetings.

Roles and Responsibilities These have pretty much been documented and agreed. We will target completing and signing off this task by 31st Jan 2019.

Policy and Procedures. We have received the bulk of the standards. These are at varying levels of completion and some are still outstanding but there is more than enough for us to progress with Procedures. We are going through the standards and identifying high level procedures. These will in turn be assigned to individuals for completion. Initial target is to complete this by end of March. 19. This represents the progress we have made on the components we have started.

 

Key Tasks For Next Period As above.

Issues As usual key issues are resource related. Operational Staff allocated to the project appear to be spending the bulk of there time on 'Operational' tasks with little or no Project work being carried out.  Technical resource is constrained by not being able to hire the agreed additional resource.

Milestones

Stage Milestone Due Date  
Analyse Clarify Dependency for Incident Management. 31-Jan-2019

view

Plan Agree Plan for SIEM (Splunk) 31-Jan-2019

view

Plan Agree Scope For IDS / IPS 31-Jan-2019

view

Plan Agree Initial Plans for All Other Components 31-Jan-2019

view

Plan Complete Plan. 28-Feb-2019

view

Deliver Complete Policy and Procedures. 31-Mar-2019

view

Close Close Project 31-Dec-2019

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Lack of resource in the Technical area is holding up our ability to clarify technical requirements and move forward.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation