Planning and Delivery are in Progress.

Report Date
February 2019

 

Report For February 2019

 

Achievements in the last Period.

Technical Controls

SIEM – Splunk Neil Kell has highlighted a standard, GPG13 (Good practice guide) that would satisfy our ISO27001 SIEM guidelines.

We had a Splunk consultant onsite last week or three days. From this we identified that our key issue would pre work that we would need to do to ingest log files which had been previously been ingested by log insight.

We have the same consultant on site next week (3rd March). I would hope by the end of that week we would have resolved that issue and be well on the way to delivering GPG13 and therefore closing all the ISO27001 risks.

There may be more work required on top of this to get us to the point of a fully functional SIEM that we can demo as a Proof Of Concept to the wider University. This may require a priority call.

 Encryption.

Key management and encryption solution selected and ordered. This is scheduled for delivery and installation early April.

Management Cluster Upgrade

We have a quote for an R630. We need this requoted with more RAM. We need a quote for the VMWare required to run on this Hypervisor.

IDS / IPS

This isn’t going ahead. See Risk Treatment plan for details.

Governance

Project Board and Security Working Group are defined and in place.

Policy and Procedures

These are in progress.

Incident Management

Meetings on-going trying to clarify the status of required standards and procedures from a Data Safe Haven Perspective.

Physical Security Review

We (A.Todd/N.Kell)  reviewed the ACF ISO27001 Scope with the EPCC ISO Person (Anne Whiting).

We agreed that the ACF Certification would in all likelyhoods cover all that is required for DSH at the ACF and Anne would send through the required documents.

Neil Carried out an initial Site Audit of the JCMB Data Centre. This will be circulated. While there were issues, we should still pass regardless once the Cage is in place.

The cage is scheduld to be deploted on the 1st Of April.

We still have a number of SOPs related to the Data Centres and key management, but these are in hand.

Medial Destruction Certificates

This will be written in due course as part of the Procedures effort.

We'll need to put a key lock into the JCMB DC. This has been agreed and will be done imminently.

 

Key Tasks For Next Period

  • As above.

 

Milestones

Stage Milestone Due Date Previous Date Complete  
Plan Complete Plan. 28-Feb-2019 No date available No

view

Deliver Governance 28-Feb-2019 No date available No

view

Deliver Roles and Responsibilities 31-Mar-2019 No date available No

view

Deliver Performance Metrics 30-Apr-2019 No date available No

view

Deliver Incident Management. 31-May-2019 No date available No

view

Deliver Complete Policy and Procedures. 31-May-2019 No date available No

view

Deliver Implement SIEM (Splunk) 30-Jun-2019 No date available No

view

Deliver Cryptography and Key management 31-Aug-2019 No date available No

view

Deliver Asset Management 30-Nov-2019 No date available No

view

Close Close Project 31-Dec-2019 No date available No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Lack of resource in the Technical area is holding up our ability to clarify technical requirements and move forward.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation