Planning and Delivery are in Progress.

Report Date
March 2019

 

Report For March 2019

 

Achievements in the last Period.

Technical Controls

SIEM – Splunk Neil Kell has highlighted a standard, GPG13 (Good practice guide) that would satisfy our ISO27001 SIEM guidelines.

We have selected and implemented Splunk as our SIEM Tool. We have also agreed that we need to implement the GPG13 Splunk application. We have a splunk consultant onsite to complete our build from the 8th – 12 of April. At this point the consultant will give a Demo of what been accomplished so far and should be treated as a Proof Of concept demo for the wider Uni. This will include the functionality included in the Enterprise Security Component which has been ordered.

 Cryptography & Key Management

Several ISO27001 risks will be mitigated by implementing Data at rest encryption and we have identified a method of doing this. We have purchased the required key Managment and encryption appliance to do this. We have an issue however that we can’t power this up at the ACF Data centre due to a shortage of UPS (Uninterruptable Power Supply) at the site. There does not seem to be a short term solution to this.

NTP (Network Time Protocol) Server.

We have a requirement to put in an NTP Server. We have a contractor due to put an aerial on the room at JCMB. We have ordered a primary NTP Server for JCMB and a slave to go at the ACF. (This architecture is due to us not being able to put an aerial on the roof at the ACF Data Centre).

Environment Patching.

OS Patching is covered within Policies and Procedures. However a further requirement to achieve the standard prescribed by Cyber Essentials Plus was required by NHS Lothian. This requires that we patch every component related to the DSH (OS, Application, server, switch, etc.) with 14 days of a critical patch coming out. This is a major overhead and we’re not at the level of frequency currently. We have vendors out looking at tools that may assist us with this going forward, but it doesn’t feel like we’re getting close to a solution. I have also gone to market to try and find a contractor that could do this manually in the short term. This may be the quickest way to progress initially.

Asset management

We have written, reviewed and signed off all the required procedures for this. Next step is to identify all the required assets to go into the asset management tool (Device 42) and get it populated. We have a contractor starting in a couple of weeks who will be picking this up.

Performance Metrics

We have documented the initial Performance Metrics. These will go through a few iterations of review and update.

Business Continuity

We are still waiting on the University Standards Document so we can progress the related Procedures.

Policy and Procedures.

We have made good progress with Procedures related to Asset Management, Access Management and Operational Security. We have a key blocking requirement around Tasks relating to Patching as a requirement for NHS Lothian and this has been prioritised accordingly. We need the Business Continuity Standard to enable us to progress Business Continuity.

Issues

We have blocking issues with UPS Power at the ACF data Centre blocking us progressing with the Encryption Solution and the NTP Server. This will also block us from putting in an additional VMWare Server that’s required.

We have an outstanding Medium Penetration Test issue that’s needs to be resolved before NHS Lothian will give us data. This has been with the Network team for a couple of Months with no Progress.

 

Key Tasks For Next Period

  • As above.

 

Milestones

Stage Milestone Due Date Previous Date Complete  
Plan Complete Plan. 28-Feb-2019 No date available No

view

Deliver Governance 28-Feb-2019 No date available No

view

Deliver Roles and Responsibilities 31-Mar-2019 No date available No

view

Deliver Performance Metrics 30-Apr-2019 No date available No

view

Deliver Incident Management. 31-May-2019 No date available No

view

Deliver Complete Policy and Procedures. 31-May-2019 No date available No

view

Deliver Implement SIEM (Splunk) 30-Jun-2019 No date available No

view

Deliver Cryptography and Key management 31-Aug-2019 No date available No

view

Deliver Asset Management 30-Nov-2019 No date available No

view

Close Close Project 31-Dec-2019 No date available No

view

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issues around the Data Centre (ACF) are holding up key ISO deliverables.
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation