ISO27001 Centification for DSH has completed the Initial Risk Analysis and planning is under way.
- Report Date
- December 2018
Report For December 2018
Achievements in the last Period.
-
Data Safe Haven – Status.
Technical Controls
SIEM - Splunk
- We have bought the licence
- On-Site Splunk Workshop with Consultant 23/1/19
- Publish 1st cut Scope and Plan – 31/1/19
- Need to clarify Security team additional requirements.
-
Cage.
- This has hit a blocker with the 50k procurement limit and needs an NCA (Non Competitive Action) letter comepleted.
- Hopefully we’ll be able to progress on that basis.
-
IDS / IPS
- We have had initial scoping discussion with a consultant from Soft Cat.
- This is with a view to giving us some options that’s will hopefully satisfy both technical and ISO27001 requirements.
- We will get initial feedback on Tuesday 15th.
- I would hope to have selected a solution and have an initial plan by 31st Jan.
-
Governance
- First Security Working Group is scheduled for next week.
- Agenda will be agreed and circulated beforehand.
- Project Board will be reinitialised two weeks later.
- ToRs have been created and distributed for both meetings.
-
Roles and Responsibilities
- These have pretty much been documented and agreed.
- We will target completing and signing off this task by 31st Jan 2019.
Policy and Procedures.
- We have received the bulk of the standards.
- These are at varying levels of completion and some are still outstanding but there is more than enough for us to progress with Procedures.
- We are going through the standards and identifying high level procedures. These will in turn be assigned to individuals for completion.
- Initial target is to complete this by end of March. 19.
This represents the progress we have made on the components we have started.
Key Tasks For Next Period
- As above.
Issues
- The Technical have been pretty well pulled into other non DSH work that is currently deemed higher priority. This will have significant impact potentially until the end of the year.
Milestones
Stage | Milestone | Due Date | |
---|---|---|---|
Analyse | Clarify Dependency for Incident Management. | 31-Jan-2019 | |
Plan | Agree Plan for SIEM (Splunk) | 31-Jan-2019 | |
Plan | Agree Scope For IDS / IPS | 31-Jan-2019 | |
Plan | Agree Initial Plans for All Other Components | 31-Jan-2019 | |
Plan | Complete Plan. | 28-Feb-2019 | |
Deliver | Complete Policy and Procedures. | 31-Mar-2019 | |
Close | Close Project | 31-Dec-2019 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days