Team Meeting 4/11/13
1. Single-Sign-on report will be ready this week.
Morna will circulate for comments.
This deliverable will be signed off on 18/11/13
2. Database migration progress
As yet untested:
2.1 CP
2.2 Stock Management
2.3 Roslin
ACTION; Garry to confirm status
Issues remaining with:
2.3 Salary Forecasting
- this is a priority issue, Mark and Anne to progress
FIN091-11
FIN091-34
FIN091-48
2.4 Saffron
FIN091-49
2.5 Library invoices
FIN091-72
2.6 Sciquest
FIN091-77
2.7 PECOS
FIN091-78
Database migration sign off will be on 18/11/13
3. DR testing
This was moved to week beginning 18/11/13 at the request of techman who could not manage to do this during the week suggested by UNIX ( 11/11/13)
This will be signed off on 25/11/13
4. Supplier Self-Service Portal
Garry stated that FIS should be able to test so that this can be signed off IN TEST by 18/11/13 with the aim of deploying to LIVE later that week.
5. Budget and further deliverables.
The project team will consider what services or servers could be decommissioned and what the effort required would be. Finance will consider whether to fund this decommissioning.
6. AOB
Ewan stated that it would be a good idea in the medium and long-term to automatically sync functional accounts and associated files between the primary and secondary database servers to assist smooth failovers. Otherwise the functional accounts one ach server risk getting out of sync. This would take up to two days effort to apply to DEV, TEST and LIVE.
Morna opened a new JIRA so that this can be considered: FIN091-79