28/8/13 Team Meeting

Attending:

Garry Robertson, Anne Finnan, Ewan Scott, Mark Lang

 

Project estimate

 

The team discussed the project estimate. Morna noted that the estimation algorithm treats variations in the estimate of 1-2-3  the same as 10-20-30 - ie regards this as evidence of uncertainty therefore skewing the estimate towards the worst case.

The team took the view that part of the reason for this uncertainty was a legacy  of incomplete testing from the precious project, FIN083. Many crons and interfaces were never tested  by project FIN083 on DEV, as a deliberate strategy to move testing unto TEST instead.  Part of the database migration process is to move many of the eFIn cron jobs into scheduled database jobs but these must all be tested on DEV first before they can be moved. The team therefore consider the estimate cannot be reduced.

 

Morna reported that WIS had approved that database migration work can proceed in the absence of an agreed estimate pending the return of Rhian from leave.

 

Morna asked Garry to alert LIz to the fact that the current estimate is greater than the project proposal estimate.

ACTION:

Garry to discuss estimate with Liz.

Morna to discuss estimate with Rhian

 

Supplier Self-Service Testing

 

Strictly speaking, WIS have not agred that work on this can proceed in the absence of an approved  brief or estimate. Howver Mark reported that the effort to put SSS into TEST would be minor and Morna asked hin to proceed wth that.

Anne asked how this would be tested - presumably a suppler will have to take part.  Anne suggested that ABS might act as a supplier for testingpurposes. Garry will ope a call asking for ABS advice on testing SSS and asking ABS if they can act as a supplier for test purposes.

 

ACTION:

Mark to put SSS into TEST

Garry to open call re testing SSS with ABS.

 

e-expenses JIRAs

 

Morna had opened a JIRA asking Douglas to remove bad data thought to be causing e-expenses to fail on old DEV. There was confusion about who had asked for this and what this meant. ( see previous minutes) Mark will review the thinking behind this.

 

ACTION

Morna will assign e-expenses bad data JIRA to Mark

 

Licences

 

We still need more on TEST. ABS have been asked to give us more but haven't doen this yet.

 

ACTION:

Garry to chase up TEST licenses with ABS

 

Old URLs

 

ACTION:

Garry will alert FIS that all old URLs  (efin41)will be deleted on Monday 2 September.

Mark will delete old URLS on Monday 2 September

 

Database LIVE migration date

 

This can't begin on Friday 18/10/13 as Mark is on annual leave.

 

ACTION:

Garry to confirm that Finance agree the update will proceed on 25/10/13

 

FIS testing of database migration

 

Garry reported that FIS had not yet begun to test eFIn  or related applications.

ACTION:

Garry to deliver FIS test plan to IS applications and report on testing progress.

 

Project Actions

 

Today's actions:

  1. Garry to discuss estimate with Liz.
  2. Morna to discuss estimate with Rhian
  3. Mark to put SSS into TEST
  4. Garry to open call re testing SSS with ABS.
  5. Morna will assign e-expenses bad data JIRA to Mark
  6. Garry to chase up TEST licenses with ABS
  7. Garry will alert FIS that all old URLs  (efin41)will be deleted on Monday 2 September.
  8. Mark will delete old URLS on Monday 2 September
  9. Garry to confirm that Finance agree the update will proceed on 25/10/13
  10. Garry to deliver FIS test plan to IS applications and report on testing progress.

 

Actions carried over from 19/8/13

 

  1. All to sign off project brief and estimate  or to raise issues if cannot sign off.
  2. Morna to open JIRA and assign to Douglas asking him to remove bad data.
  3. Garry will findout when TEST is planned to be used for training and alert trainers to work on TEST
  4. Morna will open a JIRA for Garry to note results of testing SSS in DEV
  5. Mark to confirm dataguard/trigger solution acceptable to ABS.

Actions carried over from  12/8/13

  1. Garry will contact business owners and ask them to carry out UAT for their interfaces
  2. Paul will produce a list of all cron jobs on DEV

Actions carried over from 5/8/13

  1. Ewan to summarise current  DR/backup/resilience position and proposed  possible changes for Finance