Impact
Priority and Funding
The project priority is normal and it is sponsor funded.
Impact and Dependencies
We read data from Timtabling via the RDB and EUGEX but, as before there will be no impact on these services.
As before the updates we are making to Replay Scheduler should not result in any downtime for the service, or have any impact on the main lecture recording cloud service (Echo360).
We are dependant on development being completed before our funding model changes in August 2019. To this end we have secured all resources across Applications for the updates set out in the Scheduling brief.
It may be that a smaller amount of additional application resource would be beneficial dependant on our current conversations with Echo360 in relation to the Data brief. We will have a clear path for this project after analysis in early April after our Steering Group. This should mitigate our impact in wider development resources.
We are dependant on Echo360 for delivery of the Asset Report to complete the end of year report. They have delivered a version of this before.