Several of the current Linux Web Hosting servers are running CloudLinux 6 operating system which reaches end of life in late 2020. These need to be replaced with CloudLinux 7 machines before that EoL date.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 50.0 days 9.3 days 40.9

Project Info

Project
C-Host Infrastructure Replacement
Code
COM052
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Mark Downey
Project Sponsor
Catherine Hetherington
Current Stage
Plan
Status
In Progress
Start Date
11-Nov-2019
Planning Date
14-Jan-2020
Delivery Date
02-Apr-2020
Close Date
01-May-2020
Overall Priority
Normal

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.