Report Date
November 2019
Achievements
Draft Project Brief created
Issues
Planning Project sign off milestone will need to be pushed back to 14/01/20 (from 12/12/19) after agreement from all stakeholders. This is due to not being able to get stakeholders together to agree plan and milestones. A PICCL will be created week beginning 02/12/19 to cover the Planning sign off milestone change.
Next Steps
Planning Sign off Milestone Complete
Complete Project Brief
Plan Project
Agree Milestones
Stage
Milestone
Due Date
Plan
Planning Signoff
14-Jan-2020
Deliver
Delivery Complete
02-Apr-2020
Close
Project Closure
01-May-2020
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
A slight change in that the planning sign off for this project has been pushed back to 14th January 2020 from 12th December 2019 after agreement from all stakeholders. This will have no overall change to Project and it is still anticipated that the project will deliver to the same dates. This change to the Planning milestone means that the project is Amber this month.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
3.6 days
Activity this year
3.6 days
Activity to date
3.6 days
Estimate to complete current year
46.4 days
Estimate to complete future years
0.0 days
This article was published on Dec 13, 2019