Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 GREEN GREEN GREEN GREEN No Change
Report for November 2019 November 2019 AMBER GREEN GREEN AMBER No Change

Project Info

Project
C-Host Infrastructure Replacement
Code
COM052
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Mark Downey
Project Sponsor
Catherine Hetherington
Current Stage
Plan
Status
In Progress
Start Date
11-Nov-2019
Planning Date
14-Jan-2020
Delivery Date
02-Apr-2020
Close Date
01-May-2020
Overall Priority
Normal