Organisation

Work/Task Breakdown

Planning

  • Project initiation
  • Preparation of brief
  • Project Planning 
  • Project Brief Signoff by all Stakeholders

 

System Analysis

  • List all Websites on the current Cloudlinux6 servers
  • Capture all information regarding the owners and users of all websites currently sitting on Cloudlinux6 servers
  • Capture any issues with any of the current 400+ websites

 

Build New Servers

  • Build and configure new Cloudlinux7 servers
  • Update Technical documentation(TADs)

 

Migrate and test Websites

  • Agree a schedule with business areas to migrate all websites from current Cloudlinux6 servers to new Cloudlinux7 server builds
  • User Testing of  all websites and accept that all websites are working as expected
  • Resolve any issues that resulted from the migration, working  with user groups and owners in the business area affected.

 

New Support Model put in place

  • Currently Service Management provide support for the Cloudlinux6 servers. This project will put a more robust support model in place, to support the Cloudlinux7 servers.  Technical Management will work alongside Service management on the project,  and post project, an OLA will be agreed between Service Management and Technical Management. This will mean a larger pool of people providing support for the new servers.

 

Decommission Servers

  • Decommission the Cloudlinux6  servers when all websites fully migrated and tested on the new Cloudlinux7 servers.

 

Closure

  • Closure Report
  • Submit for approval
  • Close Project

 

Resources, Skills and  Costs

Staff from Service Management and Technology Management will be the main resources involved in this Project.  Applications Management will also be involved, as required, in the project. One of the deliverables of the Project is to implement a new more robust support model post project. Service Management provide current support for the servers. It has been agreed Technical Management will work alongside Service Management for all stages of the project and will then be part of the new Support model. An OLA will be agreed between Service Management and Technical Management.

Agreed budget for Project is 50 days.

 

Project Governance

The Project Sponsor is Alex Carter, the Programme Manager is David Watters, the Business Lead is Alain Forrester and Senior User is Euan Cameron. The main project team will be made up of colleagues from Development Technology, Technology Management and Applications Management. One of the outcomes we hope to achieve in this project is to create a more robust support model, post project.  This will eliminate individuals from supporting the servers. Technology management will work with Service Management throughout the project and will then be part of the new support model.The team will meet regularly to review progress on the project and to ensure we are on target to achieve and deliver within the timescales and budget agreed. 

 

 

Project Stakeholders

Name Business Area  Project Role
Alain Forrester IS Applications, Service Management Business Lead(Project Team)
Alex Carter IS Applications, Service Management Project Sponsor
Ana Heyn IS Applications, Production Management Team Manager, Application Services Group
Andrew Hobden IS Applications, Production Management Application Support Analyst(Project Team)
David Watters IS Applications, Project Services Programme Manager
Mark Lang IS Applications, Development Technology Team Manager, Development Technology
Euan Cameron Information, Technology and Web - CAHSS Senior User
Mark Hay Operational Services Deputy Head of IT(CMVM)
Fernando Murga Munoz IS Applications, Technology Management DBA and System Administrator(Project Team)
Mark Downey IS Applications, Project Services Project Manager (Project Team)

 

 

Project Estimations

https://secure.projects.ed.ac.uk/unpublished/project/com052/estimations/initial-estimates-for-2019-202050-days

 

 

Project Info

Project
C-Host Infrastructure Replacement
Code
COM052
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Mark Downey
Project Sponsor
Catherine Hetherington
Current Stage
Plan
Status
In Progress
Start Date
11-Nov-2019
Planning Date
14-Jan-2020
Delivery Date
02-Apr-2020
Close Date
01-May-2020
Overall Priority
Normal

Documentation

Plan