Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 GREEN 50.0 days 9.3 days 40.9 Content Status In Progress Current Stage Plan Start Date Monday, 11 November 2019 Planning Date Tuesday, 14 January 2020 Delivery Date Thursday, 2 April 2020 Close Date Friday, 1 May 2020 Project information Project Code COM052 Programme ISG - Communication (COM) Session 19/20 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Complexity Simple Overall Priority Normal