Iteration 1.0B

Planning

ReleaseIterationStart DateEnd Date

Planned

Stories

Planned

Story Points

Actual

Stories

Actual

Story Points

11.0B09/12/201319/12/20135946

 

User Stories selected for development in this iteration 

RefTitleStory PointsIterationAs a . . .I want . . .So that . . .Status
4Add extra info31.0BProcurement Officerto add extra detail to the basic data from Hunterthe info is more relevant/useful to UoE usersC/Fwd
7Hide contracts/suppliers11.0BProcurement Officerto be able to restrict access to certain contracts/supplierswe can protect sensitive information from staff and/or the publicDone
21Quick search11.0BStaff Usera quick search (single field)it's nice & easy to find stuffDone
28View supplier21.0BStaff Userto see supplier detailsso that I can get the information I want without contacting ProcurementDone
29View contract21.0BStaff Userto see the contract detailsso that I can get the information I want without contacting ProcurementDone

 

Review & retrospective (learning points)

Attendees - Craig Henderson (Product Owner), Mike McMonagle (Agile mentor), Martin Jones (Developer), Dawn Nicholls (Project Manager)

  • Review of delivered User Stories
    • Supplier/contract search logic now clarified, resulting in 2 new stories
  • Retrospective (how did we do?)
    • Story 4 was not started and will be carried over to iteration 1.0C
    • Issues with Polopoly proxy on Test - Mike thinks he knows what the issue is and will look at this
    •