Iteration 1.0A

Planning

ReleaseIterationStart DateEnd Date

Planned

Stories

Planned

Story Points

Actual

Stories

Actual

Story Points

11.0A26/11/201306/12/201351238

 

User Stories selected for development in this iteration

RefTitleStory PointsIterationAs a . . .I want . . .So that . . .Status
1Import from Hunter51.0AProcurement Officerdata imported from HunterI only have to enter contract data onceDone
28View supplier21.0AStaff Userto see supplier detailsso that I can get the information I want without contacting ProcurementC/Fwd
29View contract21.0AStaff Userto see the contract detailsso that I can get the information I want without contacting ProcurementC/Fwd
39Polopoly proxy11.0AProcurement Officerstaff & the public to be able to view contract/supplier info via our procurement polopoly pagesall of our 'buying' info is in one placeDone
5User admin21.0AProcurement Officerto manage who has access to the admin systemI can give my staff access to update records but keep non-authorised users outDone

 

Review & retrospective (learning points)

Attendees - Craig Henderson (Product Owner), Mike McMonagle (Agile mentor), Jonny Mayo (Developer), Martin Jones (Developer), Dawn Nicholls (Project Manager)

  • Review of delivered User Stories
  • Retrospective (how did we do?)
    • Team seems to be working well together, Procurement Office have been responsive to requests for info.
    • Only 3 of the 5 planned stories delivered due to time lost to automated deployment issues