APPS database migration delivered |
The APPS database was successfully migrated to the new infrastructure on Wednesday 16th July. |
Morna Findlay | 21-Jul-2014 |
New date for APPS migration - 16th July |
The APPS database will be migrated to the new infrastructure on 16th July. |
Morna Findlay | 02-Jul-2014 |
NEWS database migrated to LIVE |
The NEWS database was migrated to the new infrastructure on 21-23 April. |
Morna Findlay | 30-Apr-2014 |
NEWS upgrade date announced |
The NEWS database will be migrated to new infrastructure on 21/22 April 2014.
This will ensure the long-term stability of the applications using data held on the NEWS database. |
Morna Findlay | 18-Apr-2014 |
Change of project manager |
Morna Findlay will tae over as project manager from Stephen Conlon during the week of 17th March. |
Morna Findlay | 18-Mar-2014 |
Meeting Minutes from the 13th. |
Summary of ITS103 - Core Technology updates - Status. Present : Adam Wheavil, Stevie Conlon, Maurice Apologies : Mark Lang, Ewan Scott, Stefan Kaempf
Next Meeting Thursday 27th February , Room 3.07 10:00.
General.
- APP DEV has been migrated to the new infrastructure and testing completed. - As we are now moving into TEST, can we ensure issues are now logged in JIRA. They can be linked to the WIKI for the project. The process for testing is described below , action 17.
|
Stephen Conlon | 27-Feb-2014 |
Meeting Minutes 6th February. |
Summary of ITS103 - Core Technology updates - Status. Present : Adam Wheavil, Ewan Scott, Stevie Conlon, Apologies : Mark Lang, Maurice
Next Meeting Thursday 13th February , Room 3.07 3:00.
General.
- APP DEV has been migrated to the new infrastructure and testing completed. - As we are now moving into TEST, can we ensure issues are now logged in JIRA. They can be linked to the WIKI for the project. The process for testing is described below , action 17.
|
Stephen Conlon | 12-Feb-2014 |
Meeting Minutes 30th January 2014. |
Summary of ITS103 - Core Technology updates - Status. Present : Adam Wheavil, Mark Lang, Ewan Scott, Stevie Conlon, Maurice Apologies
Next Meeting Thursday 6th February , Room 3.07
General.
- APP DEV has been migrated to the new infrastructure and testing completed. - As we are now moving into TEST, can we ensure issues are now logged in JIRA. They can be linked to the WIKI for the project. The process for testing is described below , action 17.
|
Stephen Conlon | 03-Feb-2014 |
Project Update 23rd January 2014 |
Summary of ITS103 - Core Technology updates - Status. Present : Stevie Conlon followed up individually.
Next Meeting Thursday 30th January , Room 4.09
General.
- APP DEV has been migrated to the new infrastructure. - NEWS TEST move in progress - Stefan reported that all the pre-move testing for NEWS TEST had been completed successfully. - As we are now moving into TEST, can we ensure issues are now logged in JIRA. They can be linked to the WIKI for the project.
|
Stephen Conlon | 28-Jan-2014 |
Meeting Minutes 16th January 2014 |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Mark Lang , Ewan Scott, Adam Wheavil, Stefan Kaempf Apologies : Maurice Franceschi,
Next Meeting Thursday 23rd January , Room 4.09
General.
- APP DEV has been migrated to the new infrastructure. - NEWS TEST move scheduled for w/c 20th. |
Stephen Conlon | 17-Jan-2014 |
Meeting Minutes 13th January 2014 |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Mark Lang , Ewan Scott, Adam Wheavil, Peter Jackson Apologies : Maurice Franceschi, Stefan Kaempf
Next Meeting Thursday 16th January , Room 4.09
General.
- APP DEV has been migrated to the new infrastructure. - NEWS TEST move scheduled for w/c 20th. |
Stephen Conlon | 16-Jan-2014 |
Team Meeting 19th December |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Maurice Franceschi, Mark Lang , Stefan Kaempf, Ewan Scott Apologies : Adam Wheavil
Next Meeting Friday 10th January , Room 3.07
General.
- APP DEV has been migrated to the new infrastructure. |
Stephen Conlon | 23-Dec-2013 |
Team Meeting Minutes 12/12/2013 |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Maurice Franceschi, Mark Lang , Stefan Kaempf Apologies : Ewan Scott, Adam Wheavil
Next Meeting Thursday 19th December , 4.09.
General.
- Mark is ready to progress the DEV move of APPs when the all clear is given. Mark to update group - NEWSDEV has been migrated. Ewan to update group.
New Actions and actions carried forward, |
Stephen Conlon | 19-Dec-2013 |
Record of discussion with Dev Tech and Development teams around CRON jobs. 5th December 2013 |
_____________________________________________ From: CONLON Stephen Sent: 05 December 2013 14:59 To: LANG Mark; GOOD Richard; HENDERSON Gillian; SHAW Alyson; MCMONAGLE Michael Subject: To-days CRON job chat.
Hi Guys, to recap on to-days short chin wag.
If I recall correctly, three strands to this
|
Stephen Conlon | 11-Dec-2013 |
Team Meeting Minutes 11/12/2013 |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Maurice Franceschi Apologies : Ewan Scott, Mark Lang , Stefan Kaempf, Adam Wheavil
Next Meeting Thursday 5th December , 4.09.
General. - Mark arranged meeting with development teams reps to detemine what development involvement (05/12) may be necessary. There is no budget planned for development involement in CRON or other linked DB work. |
Stephen Conlon | 11-Dec-2013 |
Minutes for 28/11/2013 |
Summary of to-days discussion ITS103 - Core Technology updates. Present Stevie Conlon, Mark Lang , Maurice Franceschi, Stefan Kaempf, Adam Wheavil Apologies : Ewan Scott.
Next Meeting Thursday 5th December , 4.09.
General. - Maurice noted that budgets on the project were tight and advised strong milestones be planned. |
Stephen Conlon | 04-Dec-2013 |
Meeting Minutes 21/11/2013 |
Summary of to-days discussion -ITS103 - Core Technology updates. Present Stevie Conlon, Mark Lang , Ewan Scott. Apologies - Adam Wheavil
General. - Mark and Ewan continue to work on APPS and NEWs repectively . Preparation progressing. Mark expects to complete prep w/c 25/11, ewan expects to complete prep for NEWS w/c 02/11. - Adam has reported that there are only 2 schemas on MIS which require to be addressed/migrated, namely BOXICMS and DIRECT. |
Stephen Conlon | 22-Nov-2013 |
Meeting Minutes 14/11/2013 |
-----Original Message----- From: CONLON Stephen Sent: 14 November 2013 10:51 To: LANG Mark; SCOTT Ewan Subject: Meeting Minutes 14/11/2013 - ITS103 - Core Technology updates.
Summary of to-days discussion -ITS103 - Core Technology updates.
Present
Stevie Conlon, Mark Lang , Ewan Scott.
- Mark almost completed investigations into prep for Apps move. - Ewan to begin prep work this week and complete next . Prior to annual leave. - Work will be done in parallel with Mark and Ewan involved. |
Stephen Conlon | 14-Nov-2013 |
Current status w/c 11/1 |
Work has started on the Apps database migration investigations The MISLIVE investigations are planned to complete this week which will be the first milestone to complete. PM to pin down dates on the migrations with User Groups as not all have confirmed or acknowledged being aware of the porject or nomnated testing personnel. |
Stephen Conlon | 11-Nov-2013 |
New Project To Upgrade Applications Core Infrastructure Technology |
IS Applications are starting projects to migrate applications databases to the new University IT applications infrastructure. The old infrastructure is nearing the end of it's lifespan and we have to move the application databases to ensure we enjoy the benefits of the new set-up in terms of speed, reliability and failover and to ensure continuity of your service. The applications involved range from PURE, Organisational Hierarchy, Space Utilisation Datamart and EVES Student Voting. |