A new database infrastructure for the University's central systems, developed by IS Applications and IS IT Infrastructure, is now available. Initial testing with Estates and Buildings (EBIS) and SOA databases is nearing completion and databases for our other systems will be migrated over the next 18 months.

David Watters 09-Sep-2013
Week ending 9th August
  • More actions in checklist completed
  • Draft patching policy & procedures distributed to project team
  • SOA healthcheck started
  • Arrangements made for migration of EBIS LIVE
  • Revised milestones submitted to WIS
  • New infrastructure patched successfully
David Watters 12-Aug-2013
Week ending 2nd August
  • Estates & Buildings management confirmed that migration not possible until late August
  • Project team looking at SOA deployment on new LIVE infrastructure as alternative to EBIS
  • Outstanding JIRAs reviewed (most closed)
  • Outstanding tasks identified and written up in wiki
  • PICCL sent to WIS advising of change to exemplar database in LIVE
  • Migration template and other procedures updated and moved to InSite
David Watters 07-Aug-2013
Week ending 26th July
  • Project team met to discuss possibility of an alternative to EBIS, or bringing migration forward through manual update of Archibus client
  • IS Applications staff, Desktop Services and Estates & Buildings contacted about these options
  • No agreement by end of week; options still being considered
  • Work on writing up patching policy continued
David Watters 30-Jul-2013
Week ending 19th July

Summary for last three weeks:

  • PICCLs covering estimate, milestones and Archibuss issue okayed by WIS
  • Project handed over to cover PM
  • Discussions continued with Desktop Services about Archibus client - suggested that earliest available date would be late September
  • Deployment of EBIS LIVE (planned for 15/07) postponed
  • PICCL to advise of difficulty round new deployment noted by WIS
  • Meeting with DTS to discuss Archibus arranged for 19/07
  • Patching policy meeting held - PM to write up notes and prepare wiki page
David Watters 18-Jul-2013
Week ending 28th June
  • User testing carried out by E & B staff - problems post-EBIS TEST refresh but these were resolved
  • Acceptance Sign Off passed on 25/06
  • Arrangements made for migration of EBIS LIVE on 15/07
  • Updated milestones & effort submitted to WIS
  • Archibus client problem escalated via management, and reported to WIS
  • Work on preparations for migration of EBIS LIVE
David Watters 28-Jun-2013
Week ending 21st June 2013
  • USD & Desktop Services consulted re Archibus client
  • User testing delayed because of this issue
  • Stage sign-off delayed because of delays to user testing
  • New milestones required but unknown - reported to WIS
  • Manual solution provided by USD - applied to E & B machines for testing
David Watters 21-Jun-2013
Week ending 14th June 2013
  • Migration of EBIS TEST restarted (Tuesday)
  • Dev Tech and Tech Man staff working on migration
  • Migration procedures updated as migration worked through
  • Migration of EBIS TEST completed - tested successfully
  • Applications testing started - first sign of problem with Archibus client
  • Resolution of Archibus issue sought with USD
David Watters 21-Jun-2013
Week ending 7th June 2013
  • Migration document for EBIS TEST prepared
  • Estimate to complete & budget increase submitted to WIS
  • Preparations made for EBIS TEST migration
  • Migration postponed until following week
David Watters 21-Jun-2013
Week ending 31st May 2013
  • More discussions on patching strategy conducted
  • Message asying that DEV environment is now available sent out to IS Apps
  • Preparation for migration of EBIS TEST started
  • Scripting of automatic repointing completed and tested successfully
  • Fast Failover scripted and tested (with positive results)
  • Issues for CSG001 (caused by DEV downtime) reported to WIS

 

David Watters 04-Jun-2013
Week ending 24th May 2013
  • Revised milestones submitted to WIS
  • 'AFM' account problem resolved & firewall issues sorted out
  • Database migration & application repoint completed
  • Switchover & failover testing carried out successfully
  • Build stage signed off (24/05)
David Watters 04-Jun-2013
Week ending 17th May 2013
  • Preparation for migration of EBIS DEV continued
  • Prep for application repoint (firewall/unix accounts)
  • 'AFM' account problem raised with ITI Unix
  • More work done on identifying outstanding tasks & effort required
  • PPBR held on 17/05 - not achieved. Reported to WIS.
  • Backups clarified with ITI Unix
  • Final checks before migration carried out.
David Watters 04-Jun-2013
Week ending 10th May 2013
  • Procedure for setting up a Standby database updated
  • Known Errors/Solutions page added to wiki
  • Added procedure for changing data protection model
  • New tns entries added to I:\TNS\tnsnames.ora
  • Migration of EBIS DEV to new infrastructure continued
  • New milestones agreed and submitted to WIS
  • New estimates of effort to complete worked out and submitted to WIS
  • Dates for migration of MyEd databases agreed with Service Management
  • All checks passed for signing off DEV environment
David Watters 14-May-2013
Week ending 3rd May 2013
  • New milestones proposed - under discussion!
  • Solution proposed for TNS issue - implemented successfully
  • ASTA updated to reflect outstanding tasks and effort required
  • Rman backup documented on project wiki
  • Migration of EBIS DEV continued [resource conflicts for Tech Man]
  • Testing of incremental backups established
David Watters 08-May-2013
Week ending 26th April 2013
  • Work continued on GRID, Rman and Active DataGuard
  • Progress made on TNS procedures
  • Procedures for standby databases & broker completed
  • Integration of ADG and GRID - failover successfully tested
  • Build sign-off milestone postponed - reported to WIS
  • Outstanding tasks and effort updated in project wiki
David Watters 08-May-2013
Week ending 19th April 2013
  • Grid upgrade ongoing - all current agents upgraded; OMS upgrade started
  • Active DataGuard setup for rman respository (rman backups running against this database)
  • Basic Implementation plan for setting up DataGuard prepared (some settings may change based on switchover/failover investigation)
  • Diagnosis of TNS issues to allow dataguard broker to failover the database.
  • EBISDEV database created on the new infrastructure
  • Review/control of dates for migration & deployment (decision due 23/04)
David Watters 23-Apr-2013
Week ending 12th April 2013
  • New mounts finalised on all servers
  • Databases discussion - all links documented and put into ER diagram
  • Agreement reached on initial layout for databases across new infrastructure
  • Consensus on GRID intallation ('option 1')
  • Alerts created for migration in live
  • Work continued on GRID & Rman
David Watters 17-Apr-2013
Week ending 5th April 2013
  • Trial migration of EBISDEV to new infrastructure
  • Documentation process further documented on Wiki
  • Agreement reached with Estates & Buildings to migrate EBIS databases
  • Set up of Active DataGuard  (and Broker) started
  • Meeting held to discuss TNS issues
David Watters 17-Apr-2013
Week ending 29th March 2013
  • Implementation of dbca templates completed
  • Database Creation procedure updated to reference standard dbca template
  • ITI Unix contacted about refresh jobs issue
  • Set-up of Active Data Guard commenced
  • Standby database established and tested successfully
  • Meeting with ITI Unix
David Watters 03-Apr-2013
Week ending 22nd March 2013
  • 11g database creation procedure updated to reflect new standards
  • Work started on creating dbca templates
  • Testing and documentation executed for different backup procedures
  • Meeting to discuss backup policy & assess best method(s) to adopt
  • New mounts agreed upon & set up
  • ASTA updated and bookings agreed with resource managers
  • Change of exemplar database required - Estates & Buildings approached re EBIS
David Watters 26-Mar-2013

Project Info

Project
Implement New Database Tier
Code
ITS100
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
16-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2013
Category
Compliance