Week ending 2nd August

  • Estates & Buildings management confirmed that migration not possible until late August
  • Project team looking at SOA deployment on new LIVE infrastructure as alternative to EBIS
  • Outstanding JIRAs reviewed (most closed)
  • Outstanding tasks identified and written up in wiki
  • PICCL sent to WIS advising of change to exemplar database in LIVE
  • Migration template and other procedures updated and moved to InSite

Project Info

Project
Implement New Database Tier
Code
ITS100
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
16-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2013
Category
Compliance

Documentation