Week ending 10th May 2013

  • Procedure for setting up a Standby database updated
  • Known Errors/Solutions page added to wiki
  • Added procedure for changing data protection model
  • New tns entries added to I:\TNS\tnsnames.ora
  • Migration of EBIS DEV to new infrastructure continued
  • New milestones agreed and submitted to WIS
  • New estimates of effort to complete worked out and submitted to WIS
  • Dates for migration of MyEd databases agreed with Service Management
  • All checks passed for signing off DEV environment

Project Info

Project
Implement New Database Tier
Code
ITS100
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
16-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2013
Category
Compliance

Documentation