Week ending 17th May 2013
- Preparation for migration of EBIS DEV continued
- Prep for application repoint (firewall/unix accounts)
- 'AFM' account problem raised with ITI Unix
- More work done on identifying outstanding tasks & effort required
- PPBR held on 17/05 - not achieved. Reported to WIS.
- Backups clarified with ITI Unix
- Final checks before migration carried out.