Week ending 17th May 2013

  • Preparation for migration of EBIS DEV continued
  • Prep for application repoint (firewall/unix accounts)
  • 'AFM' account problem raised with ITI Unix
  • More work done on identifying outstanding tasks & effort required
  • PPBR held on 17/05 - not achieved. Reported to WIS.
  • Backups clarified with ITI Unix
  • Final checks before migration carried out.

Project Info

Project
Implement New Database Tier
Code
ITS100
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
16-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2013
Category
Compliance

Documentation