Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for January 2020 January 2020 GREEN GREEN GREEN GREEN No Change
Report for December 2019 December 2019 AMBER AMBER GREEN AMBER No Change
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN No Change
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN

Project Info

Project
ASTA Upgrade
Code
INF153
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
15-Oct-2019
Planning Date
13-Dec-2019
Delivery Date
19-Mar-2020
Close Date
16-Apr-2020
Overall Priority
Normal
Category
Compliance

Documentation