Report for November 2019
- Report Date
- November 2019
Achievements since last report
- Meeting held with Elecosoft on 7th November to discuss options for upgrade and reviewing server details to understand if in place upgrade could be an option and understand where supplier can support upgrade activity
- Costs provided for supplier engagement during upgrade
- Draft estimates and review task activity
Issues
- Elecosoft advised that although there is a cloud solution available they have not yet tested Timesheet application in the cloud. As this is currently outstanding we would not be able to move to the Cloud.
- Production Management have been advised that for this project a move to a Cloud Solution is deemed not in scope
- Due to limited PM availability due to annual leave, other project commitments and also technical resource not available due to Industrial action the planning milestone has been revised and approved
Next Steps
- Arrange technical workshop
- Project brief approval and submission to WIS
- Project plan and resource assigned
The project status is GREEN
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days