User Acceptance Test (UAT) Plan

Contributors

 

Role

 Unit                 

 Name              

 Date Signed Off           

Project Manager

 

 

 

Project Sponsor

 

 

 

Business Analyst (Owner)

 

 

 

Systems Analyst Designer

 

 

 

Technical Architect

 

 

 

Add other document contributors as required              

 

 

 

 

Link to UAT Plan on Wiki

Project Info

Project
ASTA Upgrade
Code
INF153
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
15-Oct-2019
Planning Date
13-Dec-2019
Delivery Date
19-Mar-2020
Close Date
16-Apr-2020
Overall Priority
Normal
Category
Compliance

Documentation

Execute