Priority and Funding
The project is core funded and at Annual Planning stage estimated as 125 days. Planning estimate is 100 days - a review of effort will be completed on successful in place upgrade of test environment.
The project has an overall priority of NORMAL (It should be considered to be moved to HIGHER due to the EOL status of infrastructure and the software current version is eminently nearing end of support).
Impact and Dependencies
Any changes to the LIVE ASTA service will need to be managed between IS Applications MI reporting dates to minimise the impact to users.
This project is not expected to impact the IS Applications start/end of year preparations but this could become a concern if the project is not completed by July 2020. Also require to consider changes around quarterly periods e.g. end of October, January, April and July.
Due to upgrade activities it is essential that Timesheet Management is tightly controlled and monitored to ensure no outstanding timesheets remaining at time of upgrade of both Test and Live environments.
Ensure tabular reporting in ASTA is not effected and does not impact links to Power BI reports on projects website.
Project Risks
Ref | Title | Initial Risk | Current Risk | Status | Management Approach | Risk Owner |
---|---|---|---|---|---|---|
1 | 3rd party supplier are available to support upgrade | GREEN | GREEN | Open | Reduce | Dawn Holmes |
2 | Delivery timescales may deem Windows Server out of support | AMBER | AMBER | Open | Avoid | Karen Stirling |
3 | Dev Tech resource availability to support project | GREEN | GREEN | Open | Reduce | Mark Lang |
4 | Tech Management resource availability to support project | GREEN | GREEN | Open | Reduce | Heather Larnach |
5 | SQL database currently on out of support infrastructure | AMBER | AMBER | Open | Reduce | Stefan Kaempf |
6 | Current ASTA software may become end of support before upgrade can be deployed | AMBER | AMBER | Open | Retain | Rhian Davies |
7 | Availability of ITI Enterprise resource to support build / in place upgrade activities | GREEN | GREEN | Open | Reduce | Murray Dippie |
8 | In place upgrade activity deems new build required | AMBER | AMBER | Open | Reduce | Karen Stirling |
9 | Tabular reports may impact Power BI link | GREEN | GREEN | Open | Reduce | Stephanie Ruthven |