Report for December 2019

Report Date
December 2019

Achievements since last report

  • Arrange technical workshop for 6th and 14th January now completed
  • Project brief updated, project plan and estimates created 
  • Resource assigned from Dev Tech and ITI
  • Agreement to complete In place Upgrade for Operating Systems on Test environment
  • Costs provided for supplier engagement during upgrade
  • Draft estimates and review task activity

Issues

  • Confirmation Elecosoft costs to be paid from support costs or funds confirmed by project sponsor
  • Due to limited PM availability due to annual leave, other project commitments completion of project brief sign off delayed, milestones to be revised as part of planning.
  • Project brief now issued for final comments
  • Outstanding timesheets is a key risk to upgrade of both test and live draft communication has been issued to PMO for approval to project email to be issued out as well as agreed PMO communication 

Next Steps

  • Project brief approval
  • Per work for test environment upgrade
  • Create test plan
  • Data refresh from Live to Test
  • Application, Operating System and SQL upgrade planned for week commencing 27th January

 

The project status is AMBER due to delay in sign off project brief

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
This project is AMBER due to delay in signing off project brief and technical meeting not scheduled until early January now completed
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Programme Manager and Project Sponsor
Change Commentary
This project is AMBER due to delay in signing off project brief and technical meeting not scheduled until early January now completed
Activity
Approved budget
125.0 days
Activity this month
0.6 days
Activity this year
6.9 days
Activity to date
6.9 days
Estimate to complete current year
118.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ASTA Upgrade
Code
INF153
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
15-Oct-2019
Planning Date
13-Dec-2019
Delivery Date
19-Mar-2020
Close Date
16-Apr-2020
Overall Priority
Normal
Category
Compliance

Documentation