Impact

Priority and Funding

Overall Priority - Normal

Funding Source - Sponsor funded by Fraser Muir

Impact and Dependencies

This project is to deliver a proposal to improve the present online ECA induction presence.  There will be no impact on University systems, processes, or people.

Assumptions

The project will identify a number of actions and an associated development plan.  The most immediately achievable of these will be addressed during the project while more long term tasks will require to be addressed as ongoing tasks beyond the end date of the project.  Any technical effort required to address these tasks will be provided by the ECA or CAHSS.

Project Risks

(Please copy and paste from Risk Log)

Ref: Risk Description Initial Risk Current Risk Status Management Approach Risk Owner
1

Stakeholder participation.

Green Green Open Reduce Ken Miller
2 Resource unavailable to undertake Intranet improvements Green Green Open Reduce Ken Miller
3 Unable to delivery appropriate induction content Amber Amber Open Reduce Judith Miller
4 Poor perception of existing intranet. Amber Amber Open Reduce Judith Miller

Project Info

Project
ECA Induction - Analysis and support for implementation of a school intranet site
Code
HSS026
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Judith Miller
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
12-Oct-2018
Planning Date
05-Apr-2019
Delivery Date
26-Sep-2019
Close Date
22-Nov-2019
Programme Priority
7
Overall Priority
Normal
Category
Discretionary