Project Brief Estimation Details
Having estimated the project at 95 days; the following presents a breakdown of the estimated resource and associated functionality
Planning - 10 days
Planning for the Brief includes a number of meetings, setting up the project website, estimation process, and planning the tasks required
To-date 7 days have been utilised as part of the planning process (Actual 9.8 days)
Project Management - 27 days
This will provide time for
- the project manager to managing all day-to-day project activities, replanning when required, regular communication, and maintaining project website,
- additional support from programme and portfolio managers when required
Business Analysis - 22 days (used 29 and need to allocate more tasks and time + 2 remaining for Test scripts)
This relates to the estimated time for the business analyst to
- documenting existing processes (4 days) (completed)
- gather and document business requirements (6 days) (completed Works)
- review system options, assist with the proof of concept and prepare gap analysis (10 days)
- establishing Acceptance Test scripts (2 days)
Systems Design - 10 days
This relates to the following activities
- technical support incorporating the production of the relevant technical documentation - 2 days
- technical support throughout the test phase of the project - 3 days
- consultant led workshops regarding standard functionality, gap analysis and proposed configuration - 5 days (in progress)
Configuration and Integration - 8 days
This relates to
- the production of on-going technical support documentation
- handover to production for on-going support
- Refresh of DEV and TEST from LIVE
- initial system checks to ensure that the test system is fully functioning prior to user acceptance tests
Acceptance - 14 days
Whilst the majority of testing will be carried out by Estates Department staff, there will be additional time required to complete
- system load (stress) tests, incorporating the production of electronic scripts, monitoring and subsequent analysis of system performance
- technical support during this phase
- overseeing of user acceptance testing by business analyst
Deployment and Closure - 4 days
This relates to
- technical support post-go live
- closure report and project closure activity