Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for August 2018 August 2018 GREEN GREEN GREEN BLUE
Report for July 2018 July 2018 AMBER GREEN GREEN AMBER
Report for June 2018 June 2018 GREEN GREEN GREEN GREEN
Report for May 2018 May 2018 GREEN GREEN GREEN GREEN
Report for April 2018 April 2018 GREEN GREEN GREEN GREEN
Report for March 2018 March 2018 RED GREEN GREEN RED
Report for February 2018 February 2018 GREEN GREEN GREEN GREEN
Report for January 2018 January 2018 GREEN GREEN GREEN GREEN
Report for December December 2017 GREEN GREEN GREEN GREEN
Report for November November 2017 GREEN GREEN GREEN GREEN

Project Info

Project
Authentication & Authorisation improvements 17/18
Code
ENT031
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
30-Nov-2017
Planning Date
17-Jan-2018
Delivery Date
24-Aug-2018
Close Date
29-Aug-2018
Overall Priority
Higher
Category
Discretionary