Report for March 2018
- Report Date
- March 2018
Impact from Strikes : work on Galera now moved back to April where it is conflict with a high priority project. New milestone for Galera (data encryption) set. The work on EASE two-step authentication will now be lower-priority within the project, but project will still move this forward with edWeb team.
Achievements in Last Period
- meet Web Team to set out user journeys - not achieved
- broad understanding with Web team around scope and resource for design and UX - not achieved
Issues and Risks
- issue around connection problems with current Galera database
Next Steps
- meet Web Team to set out user journeys
- broad understanding with Web team around scope and resource for design and UX
Future Milestones
08-Jun-2018 | Delivery of the Quick Wins - Galera move and Rest and In Transit Encryption |
29-Jun-2018 | Delivery of the Quick Wins - EdGel and Two-Step Authorisation |
27-Jul-2018 | Closure |
Project Sponsor Commentary / Approval
- Approved budget
- 120.0 days
- Activity this month
- 10.0 days
- Activity this year
- 10.0 days
- Activity to date
- 10.0 days
- Estimate to complete current year
- 50.0 days
- Estimate to complete future years
- 40.0 days