Report for June 2018
- Report Date
- June 2018
Scope of Project changed in April :
Project will deliver this as GDPR compliance for EASE/Cosign.
Project will deliver encryption of SSL and galera database.
Project will not deliver changes to EASE login re design. However, USD will return their requirements and design elements for future 18-19 project to replace Cosign.
Achievements in Last Period
- Design document fOR review and approval - sen out
- Then these scripts packaged and deployed by lcfg to all the EASE cosign tiers after data migration 26/6. done
- Data migration. From existing database servers to LIVE galera service again om 26/6/18. done
- SSL enabled mysql connections development on 26/6/18. done
Issues and Risks
- issue around connection problems with current Galera database
Next Steps
- Design document approved
- Encryption of data held in galera. Work from around the w/c 11/6/18, then tested and then delivered soon after 26/6. Dropping Postal addresses.
- get USD/Web team requirements for future design and UX
Future Milestones
27-Jul-2018 | Delivery of the Quick Wins - Encryption of personal data Fields |
27-Jul-2018 | Delivery of the Quick Wins - Encryption of personal data Fields |
31-Jul-2018 | Closure |
Project Sponsor Commentary / Approval
- Approved budget
- 120.0 days
- Activity this month
- 4.0 days
- Activity this year
- 25.0 days
- Activity to date
- 25.0 days
- Estimate to complete current year
- 16.0 days
- Estimate to complete future years
- 0.0 days