Report for August 2018
- Report Date
- August 2018
Scope of Project changed in April :
Project will deliver this as GDPR compliance for EASE/Cosign.
Project will deliver encryption of SSL and galera database.
Project will not deliver changes to EASE login re design. However, USD will return their requirements and design elements for future 18-19 project to replace Cosign.
Achievements in Last Period
- UAT by Student Systems - done
- Closure - done
Issues and Risks
- None
Next Steps
Future Milestones
31-Aug-2018 | Closure |
Project Sponsor Commentary / Approval
- Approved budget
- 120.0 days
- Activity this month
- 4.0 days
- Activity this year
- 35.0 days
- Activity to date
- 35.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days