Progress Monthly Report

Report Date
January 2014

Achievements this period

  • Test Upgrade completed
    • Dev Tech supported Sciquest successfully from 2pm to 8pm from 7-10 Jan for TEST deployment.
  • Customer Acceptance Testing was completed  between 14-27 Jan
    • Chemistry and Procurement Testing took place simultaneously
  • Training Webinar toook place on Monday 13th January afternoon
  • Customer Acceptance Testing Signed off
  • LIVE Deployment took place 28-29th Jan 14

 

Issues
  • None 

 

Next steps
  • Release signed off 4-Feb-14 
  • Completion of handovers of project documentation
  • Support of project until Deployment Sign Off
  • DSOR and Closure will be completed by 18th Feb
 

Milestones

04-Feb-2014Release
18-Feb-2014DSOR and Closure

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
63.0 days
Activity this month
19.0 days
Activity this year
47.0 days
Activity to date
47.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days