Progress Monthly Report
- Report Date
- January 2014
Achievements this period
- Test Upgrade completed
- Dev Tech supported Sciquest successfully from 2pm to 8pm from 7-10 Jan for TEST deployment.
- Customer Acceptance Testing was completed between 14-27 Jan
- Chemistry and Procurement Testing took place simultaneously
- Training Webinar toook place on Monday 13th January afternoon
- Customer Acceptance Testing Signed off
- LIVE Deployment took place 28-29th Jan 14
Issues
- None
Next steps
- Release signed off 4-Feb-14
- Completion of handovers of project documentation
- Support of project until Deployment Sign Off
- DSOR and Closure will be completed by 18th Feb
Milestones
| 04-Feb-2014 | Release |
| 18-Feb-2014 | DSOR and Closure |
- Approved budget
- 63.0 days
- Activity this month
- 19.0 days
- Activity this year
- 47.0 days
- Activity to date
- 47.0 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days