December Report
- Report Date
- December 2013
Achievements this period
- Ensuring all in place for upgrade to proceed 7-10th Jan in TEST
- SciQuest Dev Tech Stakeholder contacted - Michael Kensky
Issues
- None
Next steps
- Test Upgrade to be completed
- Dev Tech will support Sciquest from 2pm to 8pm from 7-10 Jan for TEST deployment.
- Customer Acceptance Testing planned to be completed between 14-27 Jan
- Chemistry and Procurement Testing taking place simultaneously
- Training Date to be agreed for Webinar and any documents obtained for Chemistry
- Customer Acceptance Testing to be Signed off
- LIVE Deployment planned to take place 28-31st Jan 14
- Release planned to be signed off 4-Feb-14
Milestones
| 14-Jan-2014 | Do It |
| 27-Jan-2014 | Procurement and Chemistry Check It |
| 04-Feb-2014 | Release |
| 18-Feb-2014 | DSOR and Closure |
- Approved budget
- 77.0 days
- Activity this month
- 2.0 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 50.0 days
- Estimate to complete future years
- 0.0 days