December Report

Report Date
December 2013

Achievements this period

  • Ensuring all in place for upgrade to proceed 7-10th Jan in TEST
  • SciQuest Dev Tech Stakeholder contacted - Michael Kensky  

 

Issues
  • None 

 

Next steps
  • Test Upgrade to be completed
    • Dev Tech will support Sciquest from 2pm to 8pm from 7-10 Jan for TEST deployment.
  • Customer Acceptance Testing planned to be completed  between 14-27 Jan
    • Chemistry and Procurement Testing taking place simultaneously
  • Training Date to be agreed for Webinar and any documents obtained for Chemistry
  • Customer Acceptance Testing to be Signed off
  • LIVE Deployment planned to take place 28-31st Jan 14
    • Release planned to be signed off 4-Feb-14 
 

Milestones

 

14-Jan-2014Do It
27-Jan-2014Procurement and Chemistry Check It
04-Feb-2014Release
18-Feb-2014DSOR and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
77.0 days
Activity this month
2.0 days
Activity this year
28.0 days
Activity to date
28.0 days
Estimate to complete current year
50.0 days
Estimate to complete future years
0.0 days