November Report
- Report Date
- November 2013
Achievements this period
- Agreement reached as to how and when the project will proceed
- Agreed Project Plan with SciQuest, Procurement, Chemistry and IS Apps
- Re planned project, plan and resource bookings
- Build date agreed with SciQuest - scheduled to start 7th Jan with 1 day to check everything is in place
- Dev Tech will support Sciquest from 2pm to 8pm from 7-10 Jan for TEST deployment.
Outstanding Issues
- None
Next steps
- Training Date to be agreed for Webinar and any documents obtained for Chemistry
- January the project will proceed full on until deployment 28-31st Jan 14.
Milestones
| 14-Jan-2014 | Do It |
| 27-Jan-2014 | Procurement and Chemistry Check It |
| 04-Feb-2014 | Release |
| 18-Feb-2014 | DSOR and Closure |
- Approved budget
- 77.0 days
- Activity this month
- 3.0 days
- Activity this year
- 25.0 days
- Activity to date
- 25.0 days
- Estimate to complete current year
- 52.0 days
- Estimate to complete future years
- 0.0 days