November Report

Report Date
November 2013

Achievements this period

  • Agreement reached as to how and when the project will proceed
  • Agreed Project Plan with SciQuest, Procurement, Chemistry and IS Apps
  • Re planned project, plan and resource bookings
  • Build date agreed with SciQuest - scheduled to start 7th Jan with 1 day to check everything is in place
  • Dev Tech will support Sciquest from 2pm to 8pm from 7-10 Jan for TEST deployment.

 

Outstanding Issues
  • None 

 

Next steps
  • Training Date to be agreed for Webinar and any documents obtained for Chemistry
  • January the project will proceed full on until deployment 28-31st Jan 14.
 

Milestones

14-Jan-2014Do It
27-Jan-2014Procurement and Chemistry Check It
04-Feb-2014Release
18-Feb-2014DSOR and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
77.0 days
Activity this month
3.0 days
Activity this year
25.0 days
Activity to date
25.0 days
Estimate to complete current year
52.0 days
Estimate to complete future years
0.0 days