Team Availability

 

Please note dates below when key team members will be unavailable.

 

 

Morna absences - Nikki will stand in

Susan McLaren absences - Susan to arrange cover

Anne Finnan and John Chan to cover for each other

 

w/cMonTueWedThuFriNotes
16/5      
23/5      
30/5Pam

Pam

Terry

Pam

Terry

PamPam 
6/6

Pam

Susan

SusanSusanSusanSusan 
13/6SusanSusanSusanSusanSusan 
20/6

BUILD

     
27/6

Pam

Terry

Pam

Terry

Pam

Terry

Pam

Terry

Pam

Terry

 
4/7

Terry

ACCEPTANCE

TerryTerryTerryTerry 
11/7

Terry

DELIVERY

     
18/7      
25/7      
1/8TerryTerryTerryTerryTerry 
8/8

Terry

DSOR

     
15/8

CLOSE

     
22/8      
29/8      
       
       
       

 

Project Info

Project
Online Payslips and P60s
Code
PPP002
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
21-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2017
Overall Priority
Normal
Category
Discretionary